Construction

Multi-Phase Construction Plan for Blossomland Remodel


BLC Construction Update 11-12-18


A more detailed version of this map is available for download.


Update from Miller-Davis:

The construction team is completing A-Pod and are scheduled to move staff back in the first week of December. The gym is being cleaned and will open next week after the final inspection from the fire inspector. The pool will be inspected and tile work will start soon. The B-Pod phase of the project will begin the second week of December.